Planning Conditions and When They Must Be Discharged

When the decision notice arrives, the word "granted" is what most people see first. The list of conditions underneath deserves just as much attention, because some of them decide whether you can lawfully start work at all.

What a condition is

A planning condition is a requirement attached to a permission. Councils use conditions to make a development acceptable when it would not otherwise be, or to control details that were not fixed at application stage. Each condition comes with a reason, usually referring to a policy.

Good practice is that conditions should be necessary, relevant to planning and to the development, enforceable, precise and reasonable. In practice they range from the very simple to the quite involved.

The three kinds you will meet

1. Conditions you simply comply with

These set rules that apply throughout the life of the development. Examples include:

  • the time limit for starting work, normally five years for a full permission;
  • building in accordance with the approved drawings;
  • matching materials;
  • obscure glazing in a particular window;
  • restrictions on use, such as a garden building being used only for purposes incidental to the house.

You do not need to apply to anyone about these, but you do need to keep to them.

2. Conditions that require something before work starts

Often called pre-commencement conditions, these use wording such as “no development shall take place until”. Common examples:

  • submitting and agreeing samples of external materials;
  • a landscaping scheme for a rural house;
  • providing the visibility splays at the entrance before any other work;
  • details of foul and surface water drainage;
  • an archaeological programme of works.

These are the conditions that cause trouble. If work starts before they are formally discharged, the development may not be authorised, and in some cases the permission itself can be put at risk.

3. Conditions triggered at a later stage

Some conditions bite before occupation or within a set period, for example “prior to occupation, the parking spaces shall be provided” or “the landscaping shall be carried out in the first planting season after occupation”. Some councils also use a demolition condition on replacement dwellings, requiring the old building to be removed or its use restricted.

Conditions on outline permissions

An outline permission works slightly differently. Its conditions usually say which reserved matters (access, appearance, landscaping, layout and scale) must be approved, and by when. They may also fix parameters for the later design, such as a maximum ridge height, a single-storey limit or the position of the house within the site. A buyer of a site with outline permission should read these carefully, because they shape what can be built. See outline or full planning permission.

How to discharge a condition

Discharging a condition means getting the council’s written agreement that its requirements have been met. In Northern Ireland this is a separate submission to the council, made through the Planning Portal (or Mid Ulster’s own system) with the information the condition asks for, such as drawings, samples, specifications or reports. The council may consult the same bodies it consulted on the original application, such as DfI Roads or NI Water.

Allow for this in your programme. Discharge of conditions is not instant, and a builder waiting on site is an expensive way to find that out.

What if a condition is unworkable?

If a condition cannot reasonably be met, or circumstances have changed, it may be possible to apply to develop the land without complying with it, or with a varied version, under section 54 of the Planning Act (Northern Ireland) 2011. The council can only look at the condition in question, not reopen the whole permission. An appeal against a condition is also possible within the appeal time limit, but that is usually a last resort.

Practical tips

  1. Read the conditions the day the permission arrives and list which must be dealt with before work starts.
  2. Diarise the time limit. Note the date by which work must begin.
  3. Brief your builder. Give them the decision notice and the approved drawings, not just the building regulations set.
  4. Keep records. Photographs of the entrance works, the landscaping and the materials used can save arguments years later, for example when you sell.
  5. Ask early. If you are not sure what a condition requires, ask the council or us before you start.

Conditions and selling a property

A buyer’s solicitor will often ask for evidence that pre-commencement conditions were discharged and that occupancy conditions, such as those on some farm dwellings, have been complied with. Missing discharge letters are a common cause of delay at sale. If you are in that position, see retrospective applications and certificates.

Related reading

For the wider picture after a decision, read after a planning decision. And because building regulations are a separate system with their own approvals, see planning permission and building control.