1. Preparation
Before anything is submitted, the basics need to be pinned down: the planning history of the site, the plan the council will use, and the policy that will decide the case. This is when we check constraints such as flood risk, protected buildings, trees, access and any designations, and when drawings are prepared for the application. On a simple extension this can take a couple of weeks. On a rural house, a commercial site or anything near a sensitive designation, surveys may be needed first.
For major development there is an extra step: a proposal of application notice must be given to the council at least 12 weeks before the application is submitted, followed by community consultation. Most householder, farm and small business projects are not major development.
2. Submission through the Planning Portal
Ten of the 11 councils take applications through the shared NI Planning Portal. Mid Ulster District Council runs its own online system. An application normally includes:
- the application form for the right type of application, for example full, outline, or the householder form for works to an existing house;
- a site location plan and the drawings, usually existing and proposed plans, elevations and a block plan;
- ownership certificates and any notice to other owners;
- supporting documents where needed, such as a design and access statement, ecology or bat survey, flood risk assessment, drainage details or evidence for a farm dwelling;
- the fee. Our fees guide lists the common amounts.
3. Validation
The council checks that the application is complete and the fee is correct. If something is missing, it will be returned or held until it is put right, so getting the package right first time saves weeks.
4. Publicity and neighbour notification
In Northern Ireland the council, not the applicant, tells neighbours about the application. It serves notice on identified occupiers of neighbouring land and publishes the application in a newspaper and online. The council cannot decide the application until at least 14 days after the latest of those dates. Anyone can comment, and our article on commenting on a neighbour’s application explains how that works from the other side.
5. Consultation
The case officer asks other bodies for their view where relevant. Common consultees include DfI Roads (access and parking), NI Water (water and sewerage), DfI Rivers (flooding and drainage), the environmental and heritage teams in DAERA and the Department for Communities, and the council’s own environmental health team. Slow or negative consultation replies are one of the biggest causes of delay. Our article on site access and DfI Roads looks at the most frequent one.
6. Assessment
The case officer visits the site, weighs the proposal against the development plan and other material considerations, and reads any objections. If changes are needed, they may ask for amended drawings or more information. How you respond matters; see what to do if the council asks for more information.
7. The decision
Most applications are decided by officers under the council’s scheme of delegation. Larger or contentious cases, and those with a certain number of objections, can go to the planning committee. You will receive a decision notice granting permission, usually with conditions, or refusing it with reasons. The Department for Infrastructure decides only a small number of regionally significant or called-in applications.
How long does it take?
The official target for local applications is 15 weeks, but performance varies widely between councils. In April to June 2026 the Northern Ireland average was 20.0 weeks, according to the Department for Infrastructure’s provisional statistics. Our news item on decision times has the figures by council.
After the decision
Read the decision notice carefully. It sets the time limit for starting work and any conditions to be dealt with. Our page on after a planning decision covers the next steps.