The headline figures
- 2,390 planning applications were received in the quarter, similar to a year earlier.
- 2,295 applications were decided.
- The average processing time for local applications was 20.0 weeks, up from 19.8 weeks in the same period of 2025.
- Major applications averaged 26.1 weeks, inside the 30-week target.
- Three of the 11 councils were within the 15-week target for local applications.
The “average” processing time in the official statistics is a median.
By council
| Council | Local applications, average weeks (Apr to Jun 2026) |
|---|---|
| Antrim and Newtownabbey | 11.4 |
| Ards and North Down | 18.0 |
| Armagh City, Banbridge and Craigavon | 21.8 |
| Belfast | 18.8 |
| Causeway Coast and Glens | 20.8 |
| Derry City and Strabane | 17.3 |
| Fermanagh and Omagh | 8.4 |
| Lisburn and Castlereagh | 18.3 |
| Mid and East Antrim | 10.6 |
| Mid Ulster | 18.0 |
| Newry, Mourne and Down | 45.8 |
| Northern Ireland | 20.0 |
What this means if you are applying
These are averages for all local applications, which range from simple house extensions to complex rural and commercial schemes. A complete, well-prepared application with no consultee problems can be quicker. One that is missing information, needs surveys or attracts objections can take much longer. Our articles on what happens after you submit and replying when the council asks for more information explain where time is usually lost.
Source: Department for Infrastructure, Northern Ireland planning statistics, April to June 2026 provisional bulletin and tables.